Kreate has signed an agreement for the development stage of the alliance contract for the Kirjalansalmi and Hessundinsalmi bridges, one of the most demanding bridge projects in Finland

Share
The Finnish Transport Infrastructure Agency and Kreate have signed the development stage alliance agreement for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project, which will be one of the most demanding bridge contracts in Finland.
Timo Hirvasmaa, Jaakko Kivi and Sami Rantala from Kreate and Janne Wikström, Lars Westermark and Esa Sirkiä from the Finnish Transport Infrastructure Agency after signing the agreement for the alliance contract’s development stage for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project.
Timo Hirvasmaa, Jaakko Kivi and Sami Rantala from Kreate and Janne Wikström, Lars Westermark and Esa Sirkiä from the Finnish Transport Infrastructure Agency after signing the agreement for the alliance contract’s development stage for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project.

In the partnership-based alliance model, the Finnish Transport Infrastructure Agency and Kreate set up a joint project organisation. Besides the joint project organisation The Finnish Transport Infrastructure Agency and Kreate will set share facilities and goals, and have commonly approved cost targets. A unanimous decision is sought from all the parties regarding all the questions, and all the risks and rewards are also divided according to an agreement made in advance.

One of the most demanding bridge projects in Finland

The renovation of the bridges that cross two different straits along Saaristotie in Parainen is a technically demanding project. New bridges will be built next to the existing ones, which are the only road connection to the area. A cable-stayed bridge with a total length of more than 600 metres and a maximum span of some 250 metres will be constructed across the Kirjalansalmi strait. A cable-stayed bridge of the same magnitude was last completed in Finland nearly 30 years ago. A nearly 300-metre bridge with a maximum span of some 100 metres will be built in Hessundinsalmi. The old bridges will be dismantled once the new ones have been completed.

– The signed agreement demonstrates that Kreate’s technical expertise and capabilities for collaboration are valued. We are proud to be able to execute this exceptionally demanding bridge project together with the Finnish Transport Infrastructure Agency and leading experts, says Sami Rantala, Kreate’s Vice President for Bridge Construction and Repair.

Large industrial facilities operate behind the bridge connections, and the functionality of the bridges and the availability of routes for even heavier transport is of utmost importance to them. These transports, like other traffic, must run as seamlessly as possible throughout the entire construction.

Developing and executing together

An alliance project is always executed in two stages – the first being a development stage where the execution is planned, detailed construction plans are created and the cost targets are agreed on.

– The execution decision is only made after this. The basic principles of the alliance are transparency, trust, commonly agreed division of risks, shared responsibility, and shared decision-making in the interests of project. The negotiation process that preceded this agreement has helped us to confirm that we have the correct expertise for the project and that the prerequisites for an open, confidential collaboration are in place, says Project Manager Janne Wikström from the Finnish Transport Infrastructure Agency.

– Compared to a traditional tendering process, the negotiation process is a positively different way to start a building contract. It requires that the contractor takes a different attitude, shows its commitment and demonstrates strong competence already at the tendering stage. It is important that the contractor is involved in planning the execution starting from the initial steps of the project. This ensures that the contractor and client have a shared goal and vision regarding how the target can be reached, says Jaakko Kivi, Vice President of Kreate’s Technical Office.

In particular, the alliance model’s close collaboration between the parties is employed in order to allow the project to run smoothly as well as to allow for innovative solutions and cost savings.

The development stage will be followed by the execution stage. The aim is for the construction of the Kirjalansalmi and Hessundinsalmi bridges to begin at the latest on 1 January 2023.

The purpose of the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project is to secure the only road connection to Pargas and Turku archipelago and keep it in even better condition. It will also make HCT transport possible for the nationally significant industry located in the area. Moreover, the project supports the development of the Pargas business life and land use, and provides better traffic safety and living comfort. The cost estimate for the project complex is EUR 128 million.

Keywords

Contacts

Images

Timo Hirvasmaa, Jaakko Kivi and Sami Rantala from Kreate and Janne Wikström, Lars Westermark and Esa Sirkiä from the Finnish Transport Infrastructure Agency after signing the agreement for the alliance contract’s development stage for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project.
Timo Hirvasmaa, Jaakko Kivi and Sami Rantala from Kreate and Janne Wikström, Lars Westermark and Esa Sirkiä from the Finnish Transport Infrastructure Agency after signing the agreement for the alliance contract’s development stage for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project.
Download
Jaakko Kivi and Sami Rantala from Kreate and Esa Sirkiä and Janne Wikström from the Finnish Transport Infrastructure Agency signing the agreement for the alliance contract’s development stage for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project. On the background Timo Hirvasmaa from Kreate and Lars Westermark from the Finnish Transport Infrastructure Agency.
Jaakko Kivi and Sami Rantala from Kreate and Esa Sirkiä and Janne Wikström from the Finnish Transport Infrastructure Agency signing the agreement for the alliance contract’s development stage for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project. On the background Timo Hirvasmaa from Kreate and Lars Westermark from the Finnish Transport Infrastructure Agency.
Download

About Kreate Group Oyj

Kreate Group Oyj
Kreate Group Oyj
Haarakaari 42
04360 Tuusula

https://kreate.fi/

Kreate Group is one of the leading infrastructure construction companies in Finland. The company offers solutions for bridges, roads and railways, environmental and ground engineering, circular economy and geotechnical needs. As a specialist in demanding projects, Kreate focuses on comprehensive quality and cost-effectiveness. The group's revenue was approximately EUR 235 million in 2020 and the company has over 400 employees. Kreate Group is listed on Nasdaq Helsinki.

Subscribe to releases from Kreate Group Oyj

Subscribe to all the latest releases from Kreate Group Oyj by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from Kreate Group Oyj

Satamalaitoksen alue muuttuu vähäpäästöisesti Helsingin uudeksi asuinalueeksi – Kreate rakentaa hiilineutraalisti maalla ja meressä4.3.2024 10:00:00 EET | Tiedote

Kreate toteuttaa Nihdin urakassa maa- ja vesirakentamisen töitä osana Helsingin uuden asuinalueen rakentamista. Hanke etenee infrarakentamisen ympäristörasituksia keventäen: urakassa hyödynnetään sekä vähähiilistä betonia että työmaalla syntyvää purkubetonia, käytetään uusiutuvaa energiaa ja jätteistä valmistettua dieseliä sekä vähennetään pakokaasupäästöjä. Pelkästään vähähiilibetonin ansiosta puolitoista vuotta kestävällä hankkeella syntyy päästösäästöä jopa 200 000 CO₂-kiloa.

Kreate asentaa salaojamatot Korsvägenin rautatieasemalle Göteborgissa – yhtiön Ruotsin liiketoiminta kehittyy suotuisasti1.3.2024 09:30:31 EET | Tiedote

Kreate Sverige AB on solminut aiesopimuksen salaojamattojen asentamisesta West Link Contractors -työyhteenliittymän kanssa. Urakassa Kreate asentaa 20 000 neliömetriä salaojamattoa Korsvägenin rakenteilla olevalle rautatieasemalle ja sen tunneleihin Göteborgissa Ruotsissa. Sopimuksen arvo on noin 20 miljoonaa ruotsin kruunua eli noin 1,8 miljoonaa euroa. Inframarkkina on Ruotsissa hyvässä nosteessa, vaikka kokonaisuudessaan rakentamisen trendi on laskeva.

Pieni siirto, iso onnistuminen – Hessundinsalmen sillan harvinaislaatuisen betoninivelrakenteen tunkkaus onnistui erinomaisesti8.11.2023 13:30:50 EET | Tiedote

Paraisilla toteutetaan erittäin vaativaa siltaa, joka rakentuu tehokkaassa tahdissa valokeilassa paistatelleen kaverinsa, Kirjalansalmen sillan kanssa samalle tieosuudelle. Pituuskisassa hopealle jäävä Hessundinsalmen silta haastaa kuitenkin sillan suunnittelijat ja rakentajat teknisellä vaativuudellaan. Sen ainutlaatuinen betoninivelrakenne hakee vertaistaan Suomen historiassa, ja on tarjonnut oppimisen paikkoja jopa sillanrakentamisen huippuammattilaisille. Lokakuun lopussa Kreaten työmaalla toteutettiin betoninivelrakenteen pilarin tunkkaus: huolellisesti valmisteltu 30 millimetrin siirtymä on oleellinen seuraaville rakennusvaiheille.