Italian Lasa marble being proposed as the new facade cladding for Finlandia Hall

The Buildings and Public Areas Sub-committee of the City of Helsinki Urban Environment Committee will discuss the supplementation of the project plan of Finlandia Hall’s renovation regarding the facade on 11 June 2020. Otherwise, the project plan was completed in 2019. The project plan also included decisions on construction costs, including the cost of facade material.
The choice of facade material has been prepared for years. Durable marble types and alternative materials, both natural stone and industrially manufactured products, have been surveyed for the facade. In 2018, a test wall was erected on the roof of Finlandia Hall, where a total of eight possible facade materials have been tested. The materials have also been tested in laboratory experiments, for example by accelerating their ageing.
The Lasa Bianco Nuvolato marble, mined from the South Tyrol region, is similar in colour and pattern to the original Carrara marble, so it realises Alvar Aalto’s vision of Finlandia Hall well and the objectives of the protection decision at the same time.
Based on the test results, the lifespan of Lasa marble is estimated to be at least 50 years. The tests did not show Lasa marble to have the bowing effect common to many marble types. In addition to this, there is evidence of the durability of Lasa marble on the facades of reference buildings.
‘Finlandia Hall encapsulates the important themes in Alvar Aalto’s production and is one of his most internationally renowned works. The City of Helsinki has carefully prepared the facade project, and the research has been very thorough. Marble is a key element in the building’s architectural identity and binds together the building’s interior and facades, which form an inseparable architectural ensemble.
From the perspective of building protection, it is especially important and positive that the renovation of the facade can combine both marble and durability,’ says senior architect Sirkkaliisa Jetsonen from the Finnish Heritage Agency.
Facade to be completely renewed
Finlandia Hall’s 11,000 facade panels, their fastenings and the thermal insulation will be renewed. The surface area of the panels is 7,000 square meters.
The construction costs calculated based on the project plan are 119 million euros. The facade costs will make up some 12–15% of the overall costs, of which the material costs are less than half.
A monitoring programme has been prepared for the quality assurance of Lasa marble in cooperation with the supplier. The entire production chain of the stone is reliable and traceable, as the stone is mined and the panels manufactured by the same company.
Finlandia Hall will serve throughout the renewal project
Finlandia Hall will continue to be used as a conference and event centre throughout the renewal project.
Finlandia Hall is a heavily used event centre for concerts, conferences, trade fairs, corporate events and celebrations, with about 800 events held annually. During its 50-year history, Finlandia Hall has become the most internationally known conference centre and concert hall in Finland.
Thanks to the renewal project, the building will also receive facilities for new services. For example, an audiovisual exhibition and a design shop are being planned. In order for the restaurant to continue to be able to serve large events and conferences, the kitchen will be modernised.
Thanks to an event space called Little Finlandia, Finlandia Hall will remain open to customers throughout the renewal project. The plans for Little Finlandia have progressed during the spring of 2020, and the City is currently tendering for a contractor for the building.
The main building of Finlandia Hall, completed in 1971, is nearly 50 years old. According to condition examinations, the building is in need of an extensive renovation. Finlandia Hall will be repaired and restored from top to bottom and renovated from the plumbing to the facade. New services targeted at consumers will be located in the building while observing Alvar Aalto’s legacy and the protection the construction enjoys.
The modernisation will start in early 2022 and take about 2.5 years. The work will be completed and the building taken into use in two phases: the conference wing in spring 2023, and the main building in summer 2024.
Keywords
Contacts
Renewal project
City of Helsinki
Urban Environment Division
Sari Hildén
Head of Built Assets Management
tel. +358 (0)50 559 2125, please send any callback request messages via SMS sari.hilden@hel.fi
Finnish Heritage Agency
Sirkkaliisa Jetsonen
Senior Architect
tel. +358 (0)295 33 6274
sirkkaliisa.jetsonen@museovirasto.fi
Finlandia Hall Ltd
CEO Johanna Tolonen
tel. +358 (0)40 551 3168
johanna.tolonen@finlandiatalo.fi
Images







Links
- Lasa Marmo online
- Media bulletin 15 January 2020: Finlandia Hall to serve customers during the renovation – decision to be made on the project plan for the temporary facilities called Little Finlandia
- Media bulletin 4 February 2019: Renewal of Finlandia Hall to the 2020s – project plan advancing to decision-making phase
- Photos and an infographic of Finlandia Hall in the City’s Media Bank
- The sub-committee’s meeting materials (in Finnish)
About Helsingin kaupunki, kaupunkiympäristön toimiala

PL 58200, 00099 Helsingin kaupunki
09 310 2611http://www.hel.fi/kaupunkiymparisto
Kaupunkiympäristön toimiala huolehtii Helsingin kaupunkiympäristön suunnittelusta, rakentamisesta ja ylläpidosta, rakennusvalvonnasta sekä ympäristöön liittyvistä palveluista.
Subscribe to releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Subscribe to all the latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Pihlajiston Montusta kaikkien tila ja tapahtumapaikka9.6.2025 16:51:41 EEST | Tiedote
Salpausseläntien ympäristöä Pihlajistossa halutaan kehittää nykyistä viihtyisämmäksi ja toimivammaksi. Samalla on tarkoitus uudistaa ostoskeskuksen vieressä, katutason alapuolella sijaitsevaa ”Monttu”-nimellä tunnettua aukiota. Kaupunkilaiset voivat tulla kertomaan ajatuksiaan alueen kehittämisestä Helsinki-päivänä Point Break Monttu -tapahtumaan sekä vastata Kerrokantasi-kyselyyn.
Härbärge, strandvilla eller mormorsstuga – staden säljer fyra byggnader för bostadsbruk6.6.2025 15:42:23 EEST | Pressmeddelande
Helsingfors stad avstår från fyra bostadsbyggnader som den äger. Man säljer byggnaderna som redan är kända som Toukolakoti och Villa Notsund i Majstad och Nordsjö. Dessutom kommer två gamla trähus på Degerö att auktioneras.
Asuntola, merenrantahuvila vai mummonmökki – kaupunki myy neljä rakennusta asuinkäyttöön6.6.2025 15:42:23 EEST | Tiedote
Helsingin kaupunki luopuu neljästä omistamastaan asuinrakennuksesta. Myynnissä ovat jo Toukolakotina sekä Villa Notsundina tunnetut rakennukset Toukolasta ja Vuosaaresta. Lisäksi huutokaupattavaksi tulee kaksi vanhaa puutaloa Laajasalosta.
Specialised housing unit, seaside villa or grandma’s cottage – Helsinki selling four buildings for residential use6.6.2025 15:42:23 EEST | Press release
The City of Helsinki has decided to sell four residential buildings that it owns. Bids are already being accepted for the buildings known as Toukolakoti and Villa Notsund in Toukola and Vuosaari, respectively. In addition to these, the City will auction off two old wooden houses in Laajasalo.
Uuden päiväkodin rakentaminen on alkanut Meri-Rastilassa6.6.2025 08:15:00 EEST | Tiedote
Kaupunki rakentaa Meri-Rastilaan Harbonkadun varrelle uudet varhaiskasvatustilat noin 140 lapselle. Kohteen suunnittelussa on huomioitu sen herkkä lähiympäristö. Tilat on tarkoitus ottaa käyttöön tammikuussa 2027.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom