Permission to increase the power of Olkiluoto 3
Once authorized, TVO will gradually increase the power of the reactor from 60% to its full thermal power of 4300 megawatts. During this increase, the plant provider and TVO will ensure that the plant functions as planned also at these power levels. STUK monitors the power increase on site.
According to Essi Vanhanen, Project Manager responsible for regulatory control of OL3 at STUK, the commissioning tests carried thus far and related reports have shown that Finland's newest nuclear plant unit has operated safely and the reactor power can be increased further according to commissioning testing plans.
The commissioning tests were delayed when detached parts of the steam guide plates were found in the turbine reheater in May. After repairs and inspections, TVO submitted a report to STUK, stating that the incident did not compromise nuclear safety and that commissioning of the plant can be safely continued.
When the reactor power was increased after the repair shutdown, TVO and the plant supplier discovered that the plant's operational automation software still needed to be updated. TVO submitted a report on the matter to STUK and after the update, TVO and the plant supplier continued the commissioning as planned.
More detailed information on STUK’s surveillance observations can be found from the “Surveillance news” section of the stuk.fi website.
Keywords
Contacts
Project Manager Essi Vanhanen, tel. +358 9 7598 8242
Media contacts
Tel:+358(10)8504761Links
About Säteilyturvakeskus (STUK)
Subscribe to releases from Säteilyturvakeskus (STUK)
Subscribe to all the latest releases from Säteilyturvakeskus (STUK) by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Säteilyturvakeskus (STUK)
MetroPOEM och spåren av föroreningar30.9.2025 11:21:28 EEST | Pressmeddelande
Det europeiska forskningsprojektet MetroPOEM, som utvecklat mätning och spårbarhet av radioaktiva och icke-radioaktiva miljöföroreningar, har nått sina mål.
MetroPOEM - saasteiden jäljet selville30.9.2025 11:21:28 EEST | Tiedote
Radioaktiivisten ja ei-radioaktiivisten ympäristösaasteiden mittaamista ja saasteiden jäljitettävyyttä kehittänyt eurooppalainen tutkimusprojektiprojekti, MetroPOEM, saavutti tavoitteensa.
MetroPOEM – Tracing Pollution30.9.2025 11:21:28 EEST | Press release
The European research project MetroPOEM, which focused on improving the measurement and traceability of both radioactive and non-radioactive environmental pollutants, has successfully achieved its goals.
Säteilyturvallisuuspäivät kerää säteilyn käyttäjät yhteen9.9.2025 13:58:35 EEST | Tiedote
Säteilyturvakeskus järjestää syyskuun 10. ja 11. päivä Helsingin Messukeskuksessa Teollisuuden ja tutkimuksen 15. säteilyturvallisuuspäivät säteilyn käytöstä vastaaville ja säteilyn käyttöön osallistuville teollisuuden, tutkimuksen, opetuksen ja kaupan ammattilaisille.
STUK påminner arbetsplatserna i fem kommuner om radonmätningar2.9.2025 13:51:41 EEST | Pressmeddelande
Strålsäkerhetscentralen har skickat arbetsplatser i Pukkila, Hausjärvi, Mäntsälä, Orimattila och Miehikkälä ett brev där den begär utredning av radonhalten i arbetsplatsens arbetsutrymmen.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom
