The City of Espoo promotes the City Rail Link project
The Espoo City Board proposes that the City Council approve an amendment to the agreement between the Finnish Transport Infrastructure Agency and the cities of Espoo and Kauniainen concerning the planning and construction of the Espoo City Rail Link and separate projects related to it.

The City Board proposes that the City Council approve an amendment to the agreement between the Finnish Transport Infrastructure Agency and the cities of Espoo and Kauniainen concerning the planning and construction of the Espoo City Rail Link and separate projects related to it.
According to the amended agreement, Espoo’s share of the costs of the Espoo City Rail Link is 40.9%, but not exceeding EUR 142.8 million. In the original agreement, Espoo’s share was 40.0%, but not exceeding EUR 110 million. The estimated total cost of the project is EUR 357 million. The original cost estimate approved by the state and the municipalities was EUR 275 million.
According to the agreement, the state’s share of the costs is 51.2%, but not exceeding EUR 178.5 million. According to the original agreement, the state’s share was 50%. The City of Kauniainen’s share is 7.9%, but not exceeding EUR 27.5 million. The percentage decreased because Kauniainen has decided to make the park-and-ride facility, which was included in the original plan, a conditional project. Kauniainen’s share will remain unchanged in terms of euros.
The increase in the cost estimate is due to the general increase in costs.
The planning of the City Rail Link project has received CEF funding, and the intention is to apply for funding for its construction as well. It is estimated that the City of Espoo will receive approximately EUR 30 million of the funding granted. In addition, it is possible to allocate EUR 10–20 million to the project in the form of land use agreement revenue from the City Rail Link station areas that are under development.
Espoo City Rail Link will improve the punctuality and efficiency of train services
The Espoo City Rail Link is a joint project of Espoo, Kauniainen and the Finnish Transport Infrastructure Agency to build two new tracks between Leppävaara and Kauklahti. They will improve the punctuality and smooth flow of long-distance traffic to and from Turku and local traffic in Karjaa, Kirkkonummi and Espoo as part of the capital region public transport system.
Once completed, the two southern tracks will serve commuter trains and the two northern tracks will be used by long-distance trains. The station environments along the rail link will also be developed in line with the railway plan.
The City of Espoo will carry out its own separate projects in connection with the City Rail Link project, including Rantaradanbaana with the aim of improving cycle and pedestrian routes along the railway line.
Keywords
Contacts
Olli IsotaloDeputy Mayor for Urban Environment
Tel:+358 50 593 3359olli.isotalo@espoo.fiImages

Links
Subscribe to releases from Espoon kaupunki - Esbo stad
Subscribe to all the latest releases from Espoon kaupunki - Esbo stad by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Espoon kaupunki - Esbo stad
Tila- ja asuntojaosto: Leppäsillan päiväkoti peruskorjataan28.4.2025 09:46:53 EEST | Tiedote
Kaupunginhallituksen tila- ja asuntojaosto hyväksyi Leppävaaran Karakalliossa sijaitsevan Leppäsillan päiväkodin peruskorjauksen hankesuunnitelman.
Liikuntalautakunta päätti vuoden 2025 liikuntatoiminta-avustuksista sekä erityisryhmien avustuksista24.4.2025 19:14:25 EEST | Tiedote
Liikuntalautakunta päätti kokouksessaan 24.4.2025 liikuntatoiminta-avustuksista, lausui liikunnan infrahankkeiden investointitarpeista sekä päätti Leiki ja liiku -toiminnasta.
SM-viikko järjestetään Espoossa myös vuonna 202623.4.2025 08:00:00 EEST | Tiedote
Espoo toimii SM-viikon isäntäkaupunkina sekä tänä että ensi vuonna. Vuonna 2026 SM-viikko järjestetään kymmenettä kertaa ja ajankohtana on heinä-elokuun vaihde 30.7.–2.8.
Tiedote kasvun ja oppimisen lautakunnasta 15.4.202515.4.2025 20:50:51 EEST | Tiedote
Kasvun ja oppimisen lautakunta päätti 15.4.2024 kokouksessaan perusopetuksen lukuvuoden 2025-2026 oppilaspaikoista vuosiluokilla 1-6. Lautakunta päätti myös, että yksiryhmäisen Auroranniityn päiväkodin tilasta luovutaan vuokrasopimuksen päättyessä ja että, Saunalahden koulussa aloittavat 7. luokkien englannin ja espanjan A-kielten ryhmät syksyllä 2025.
Kaupunginhallitus: Esport Arenan lainalle lyhennysvapaata15.4.2025 19:36:42 EEST | Tiedote
Kaupunginhallitus hyväksyi kokouksessaan Esport Arenalle myönnetyn lainan lyhennysvapaan ja päätti ostaa Kameleonten Ab:n omistaman kiinteistön Viherlaaksosta. Lisäksi se hyväksyi tulevan valtuustokauden poikkihallinnolliset kehitysohjelmat sekä hallintosäännön tarkistukset.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom