Runeberginkatu intersection repaired in connection with the Mannerheimintie renovation this summer – trams diverted
Lines 2, 4 and 10 will circumvent the intersection via Ruusulankatu and Töölön halli. Line 1 will be moved to run through Kallio. The exceptional tram routes will be valid between 3 June and 1 September. The intersection work site will be busy all summer.

All of the municipal infrastructure under the surface of the street will be renovated in the intersection, including water management pipes and wells, electrical wiring and communications cables. Tram rails, asphalt, paving, poles, lighting, traffic lights, signage portals and traffic signs will also be renewed at the same time.
“There is plenty to renew in the intersection, and we will be working intensely during the tram service interruption, even at night, if necessary. We may have to move work related to installing rails, for example, to the coolest time of day, meaning the night, due to hot weather,” says project director Antti-Juhani Lehtinen from the City of Helsinki.
Work in the intersection will impact traffic arrangements on Mannerheimintie all the way to Sibeliuksenkatu. The work will generate noise, dust and vibration in the local area over the summer. The work in the intersection will commence in late May with putting the traffic arrangements in place.
Tram lines to run through Ruusulankatu and Töölön halli
Lines 2, 4 and 10 will be diverted to Töölön halli and Ruusulankatu.
Line 1 will be diverted to Kallio and Hakaniemi for the summer. The Helsinginkatu and Töölö stretches will not be operated.
Line 8 between Arabia and Jätkäsaari will be replaced by bus line 8X during the summer. It will run the normal line 8 route, but mainly use bus stops.
Read more about public transport routes in the news article published by Helsinki Region Transport (HSL).
Impacts on traffic
The work will cause major changes to traffic arrangements in the intersection over the summer. Daily changes may be made to traffic arrangements and traffic may become congested. Diversions bring changes to using all modes of transport.
All properties, buildings and ground level premises will be accessible and vehicle access to courtyards will be ensured throughout the works. The Opera and Töölö Sports Hall will also be accessible via the intersection.
Motor vehicles: Cars can be driven in all four directions from the intersection, but the road lanes will be narrowed down to one lane. The routes may be changed daily.
Pedestrians: Pedestrian access around the intersection will remain, but all pedestrian crossings will be removed from use. Replacement crossings will be located 50–100 metres away.
Cycling traffic: Bike lanes near the intersection will be in use, but bike crossings will be moved. It is recommended that cyclists divert to cycling routes in the Töölönlahti bay area.
Alternative routes around the work site
Motor vehicles can be driven across the Opera work site throughout the renovation. It is, however, recommended that drivers take alternative routes, if possible. See map of routes.
First stage of renovation to be completed by September
The first stage of the renovation between Postikatu and Runeberginkatu will be completed by September. So far, the first stage is on schedule.
The second stage of the renovation between Runeberginkatu and Reijolankatu will start in September. The renovation of Mannerheimintie will be completed by the end of 2025.
In the autumn, trams will return to Mannerheimintie between Runeberginkatu and Arkadiankatu, but will then be removed from between Runeberginkatu and Reijolankatu. The City and HSL will provide further information on the work starting in the autumn and any changes to public transport in May and June.
Contacts
Renovation in general:
Antti-Juhani Lehtinen
Project Director, Project Construction
Urban Environment Division
tel. +358 9 3103 8872
anttijuhani.lehtinen@hel.fi
Practical matters concerning the renovation:
Main contractor VM Suomalainen Oy
Ville Piironen
Site Manager
tel. +358 50 572 2143
info@manskunkatutyot.fi
Traffic arrangements:
Mikael Saarinen
Project Manager
Ramudden Oy
tel. +358 44 755 2020
mikael.saarinen@ramudden.fi
Images
Alternative languages
Subscribe to releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Subscribe to all the latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Kaupunkiympäristölautakunnan päätöstiedote 9.9.20259.9.2025 20:01:38 EEST | Tiedote
Helsingin kaupunkiympäristölautakunta kokoontui tiistaina 9.9.2025. Kokouksen päätöstiedote (yhteenveto tehdyistä päätöksistä) on julkaistu kaupungin verkkosivuilla: Päätöstiedote » Päätöstiedote näkyy verkkosivuilla siihen asti kun kokouksen pöytäkirja julkaistaan. Pöytäkirja korvaa valmistuttuaan päätöstiedotteen.
Renoveringen av Mannerheimvägen blir klar tre månader i förtid9.9.2025 13:14:00 EEST | Pressmeddelande
Helsingfors hittills största gaturenovering blir klar i förtid i september. Det ursprungliga slutdatumet för renoveringen var i slutet av år 2025. Spårvägstrafiken återvänder mellan Runebergsgatan och Grejusgatan måndagen den 8 september.
Mannerheimintien remontti valmistuu kolme kuukautta etuajassa9.9.2025 13:14:00 EEST | Tiedote
Helsingin tähän asti suurin kadun peruskorjaus valmistuu etuajassa syyskuussa. Alkuperäinen valmistumisaika oli vuoden loppu 2025. Raitioliikenne palasi Runeberginkadun ja Reijolankadun välille maanantaina 8. syyskuuta.
Nedre Malms park renoveras för att betjäna användare i olika åldrar8.9.2025 13:32:58 EEST | Pressmeddelande
Målet är att öka aktiviteter, trivseln och attraktiviteten i parken för olika användare såsom barnfamiljer och äldre. Arbetet inleds i mitten av september och blir klart i slutet av nästa år.
Ala-Malmin puisto peruskorjataan palvelemaan eri-ikäisiä käyttäjiä8.9.2025 13:32:58 EEST | Tiedote
Tavoitteena on lisätä puistoon tekemistä, viihtyisyyttä ja houkuttelevuutta erilaisille käyttäjille kuten lapsiperheille ja ikääntyneille. Työ alkaa syyskuun puolivälissä ja valmistuu vuoden 2026 lopulla.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom