Maintenance and construction work will limit electricity transmission capacity between Sweden and Finland in the summer
The transmission capacity of the cross-border electricity transmission connection between Northern Finland and Sweden will be lower than usual in the summer due to maintenance and construction work on transmission lines. The modifications and measurements carried out during the outage ensure the operational reliability and safety of the cross-border transmission connection.
![](/data/images/public/69819787/70255502/6343047a-4fa0-4a25-a918-bf26001cdd04-w_720.jpg)
Work to improve the reliability and operational safety of the cross-border transmission connection will be carried out on transmission lines in northern Sweden in early summer, which is why part of the cross-border electricity transmission connection between Finland and Sweden will be out of service. During the limitation period, the transmission capacity of the connection from Finland to Sweden will be 300 megawatts (usually 1100 megawatts) and the transmission capacity of the connection from Sweden to Finland will be 200 megawatts (usually 1200 megawatts). The estimated duration of the interruptions is just over three weeks.
A similar restriction will be repeated in July and August, when the construction work of the Aurora Line transmission line will continue with an interruption of approximately four weeks. The Aurora Line is a new cross-border transmission connection implemented jointly by Fingrid and Svenska kraftnät, which, when completed in 2025, will significantly increase transmission capacity between Finland and Sweden. The Aurora Line transmission line is 380 kilometres long and runs from the Pyhänselkä substation in Muhos all the way to Messaure in Sweden.
The construction of the first phase of the Aurora Line began in autumn 2022 in Finland. In addition to increasing transmission capacity, Aurora Line will improve the security of electricity supply and the resilience of the electricity system not only in Finland and Sweden, but also more widely in the entire Baltic Sea region.
Restrictions on cross-border transmission connections increase sensitivity to fluctuations in electricity prices
During border capacity limitations, sensitivity to fluctuations in electricity prices increases. In particular, price fluctuations may be greater than usual in situations where there are simultaneously several influencing factors, such as low or high wind power production, disturbances in power plants or disturbances in other transmission connections.
In addition, there will be several outages in Ostrobothnia during the summer because of construction work strengthening the main grid , during which the maximum production of wind power will have to be limited regionally by a maximum of 2,000 megawatts due to system security.
"Cross-border transmission connections to Sweden and Estonia are very important for the functioning of the electricity market and the system security of the Finnish electricity system. At the moment, the main grid is being built at a rapid pace in Finland and Sweden, which also causes restrictions and interruptions in electricity transmission. Fingrid and Svenska kraftnät work closely together on both sides of the border to ensure that necessary outages cause as little inconvenience as possible," says Tuomas Rauhala, Director of Power System Operations at Fingrid.
Additional information:
Senior Advisor Timo Kaukonen, phone +358 40 545 2124
Unit Manager Mikko Piironen, phone +358 50 599 0141
Email addresses are in the format etunimi.sukunimi@fingrid.fi
Keywords
About Fingrid Oyj
Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.
Fingrid delivers. Responsibly.
www.fingrid.fi
Alternative languages
Subscribe to releases from Fingrid Oyj
Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fingrid Oyj
Fingrid-konsernin puolivuosikatsaus 1.1.-30.6.202425.7.2024 11:51:39 EEST | Tiedote
Konsernitilinpäätös on laadittu kansainvälisten tilinpäätösstandardien (International Financial Reporting Standards IFRS) mukaisesti. Puolivuosikatsaus on laadittu IAS 34 Osavuosikatsaukset -standardin mukaisesti ja siinä on noudatettu konsernin vuoden 2023 tilinpäätöksessä esitettyjä laatimisperiaatteita. Puolivuosikatsaus on tilintarkastamaton. Vertailuluvut suluissa viittaavat edellisvuoden vastaavaan jaksoon, ellei toisin mainita. Fingridin kantaverkon siirtovarmuus oli korkea 99,9995 (99,99991) prosenttia. Fingridin verkossa sähköä siirrettiin 82 (81) prosenttia Suomen kokonaissiirrosta. Suomen sähkön kulutus kasvoi 42,7 (39,9) terawattituntiin Yhtiön investointiohjelma etenee suunnitelmallisesti ja investoinnit olivat edellisvuotta korkeammat. Yhtiö arvioi seuraavan neljän vuoden bruttoinvestointien määrän olevan noin kaksi miljardia euroa, joista on sidottu vajaa puolet. Kantaverkkoon liitetyn uusiutuvan tuotantokapasiteetin määrä kasvoi 585 (772) MW. Uusien hankkeiden kantaverk
Sähkömarkkinat kiinnostavat kuluttajia, vaikka ne koetaan epäselvinä26.6.2024 10:22:31 EEST | Tiedote
Sähköstä on tullut kuluttajia kiinnostava tuote. Lähes puolet suomalaisista (49 %) ilmoittaa kiinnostuksensa sähkömarkkinoita kohtaan kasvaneen. Melkein yhtä suuri osa (46 %) seuraa pörssisähkön hintaa viikoittain. Kuluttajia mietityttää korkea sähkön hinta ja hintavaihtelut. Hintaa seurataan, mutta suurin osa suomalaisista (70 %) ei kuitenkaan ole tehnyt muutoksia omaan sähkön käyttöönsä. Tiedot käyvät ilmi Fingrid Oyj:n Innolinkillä teettämästä kuluttajatutkimuksesta.
Kantaverkon sähköasemaa laajennetaan Tammistossa25.6.2024 09:07:39 EEST | Tiedote
Vantaan Tammiston sähköasemalla on keskeinen rooli pääkaupunkiseudun sähkönsiirrossa. Kantaverkkoyhtiö Fingrid rakentaa asemalle kolmannen muuntajan, jolla mahdollistetaan pääkaupunkiseudun verkon kehittäminen ja lämmityksen sähköistyminen.
Fingrid Oyj:n taloudelliset tiedotteet 202520.6.2024 11:06:09 EEST | Tiedote
Fingrid-konserni julkaisee vuonna 2025 seuraavat taloudelliset tiedotteet: 4.3.2025 tilinpäätöstiedote, toimintakertomus ja tilinpäätös vuodelta 2024 28.4.2025 johdon katsaus 24.7.2025 puolivuosikatsaus tammi - kesäkuulta 2025 28.10.2025 johdon katsaus Varsinainen yhtiökokous on suunniteltu pidettäväksi 2.4.2025. Lisätiedot: Talous- ja rahoitusjohtaja Jukka Metsälä, Fingrid Oyj, puh. 030 395 5213
Fingrid Oyj’s financial releases in 202520.6.2024 11:06:09 EEST | Press release
Fingrid Group will publish the following financial reports in 2025: 4.3.2025 Financial Review, Annual Report and Financial Statements 2024 28.4.2025 Management’s Review 24.7.2025 Half-Year Report January–June 2025 28.10.2025 Management’s Review The Annual General Meeting is scheduled to be held on 2 April 2025. For more information: Chief Financial Officer Jukka Metsälä, Fingrid Oyj, tel. +358 30 395 5213
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom