Trees in key flying squirrel habitat spared in Lapinlahti Park – Harbour tunnel location specified
Further planning of the Harbour Tunnel continues. The plan area of the tunnel connecting Jätkäsaari harbour area with Länsiväylä has been narrowed down to only include the ending of the alignment at the southern edge of the Lapinlahti hospital park. The plan now solves the conservation issues for two endangered species. Construction will not take place at the park section that includes a key flying squirrel habitat at the western end of Lapinlahti. The City Council will decide on the detailed plan of the Harbour Tunnel in late 2025 at the earliest.

Advances in the protection of endangered animals
The aim of the City of Helsinki and the Port of Helsinki is to keep the environmental impact of the tunnel as low as possible and to minimise the need to cut down trees. Special construction techniques will be used to dig the tunnel, which enables a shorter-than-planned open pit. In this case, the trees in the key flying squirrel habitat on the west side of the tunnel entrance in Lapinlahti will be spared. The construction work will be scheduled in a way to allow the protected flying squirrels to nest in peace during the construction work.
Construction of the tunnel can only begin after the population of endangered depressaria chaerophylli moths has been successfully moved to a new location. This moth feeds on the rare turnip-rooted chervil. The search for a new location for these plants, which need to be moved for the construction, is underway. There are attempts to grow new plants from seedlings as well as by planting seeds. Testing for both methods is underway and their success is being monitored. The intention is to increase the amount of turnip-rooted chervil in the Lapinlahti area.
Reservation in the city plan for the West Baana
An area has been reserved in the detailed plan for the West Baana, which will travel from the inner city to Espoo. It is a significant part of the network of cycle paths that is under construction. The West Baana will be see detailed planning at a later stage, but the relevant policies for the Harbour Tunnel are being made now. The construction of the cycle path is scheduled for the beginning of the 2030s. The placement of the cycle path aims to utilise the area used for the tunnel construction.
Makasiiniranta for residents, smoother flow of traffic in southern Helsinki
The tunnel will free Makasiiniranta for the use of residents of especially for Jätkäsaari and Ruoholahti, but also the wider South Helsinki. A museum of architecture, office buildings and a shore path are planned for Makasiiniranta, which is currently used by the port.
In the future, ferry traffic to Stockholm will depart from Katajanokka and the ferry traffic to Tallinn will depart from the West Harbour. The tunnel improves vehicle access to the West Harbour and reduces all harbour-related traffic in the city centre by about 75%, as there are considerably more passenger cars and lorries on the Tallinn ferries than on the Stockholm ferries. The tunnel is intended for port traffic only, as it will end in the port area.
The Urban Environment Committee will discuss the detailed plan proposal in early 2025
The planning of the port tunnel began in 2022. After that, a general plan for the tunnel has been completed, the impact assessment of which was completed in spring 2024. An option with an entrance between the Lapinlahti park and the Ilmarinen building was chosen as the basis of the detailed plan.
The participation and evaluation plan of the detailed plan has been updated, as the planning area now includes only the alignment that ends at the southern edge of Lapinlahti. The underground location of the tunnel will be specified during the planning process, due to which it includes a wider area than the current alignment.
In addition to taking nature values into account, the City of Helsinki and the Port of Helsinki are also conducting other studies and assessments on the technical implementation of the tunnel.
Comments on the updated participation and evaluation plan can be submitted until 15 November to the Helsinki City Register Office.
The objective is that the detailed plan proposal will be submitted to the Urban Environment Committee for consideration in early 2025 and decided by the City Council in late 2025 at the earliest. According to this schedule, the tunnel would open in 2032.
Keywords
Contacts
Otso Huhtala
Architect
City of Helsinki
09 31037296, otso.huhtala@hel.fi
Janne Prokkola
Head of Unit
City of Helsinki
09 31037233, janne.prokkola@hel.fi
Images




Links
Alternative languages
Subscribe to releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Subscribe to all the latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Detaljplanen för Hamntunneln är klar – reviderat planförslag till beslutsfattande17.10.2025 11:10:41 EEST | Pressmeddelande
Detaljplanläggningen av Hamntunneln från Västra hamnen till Västerleden är nu inne på slutrakan. Tunneln förbättrar trafikflödet på Busholmen och i södra Helsingfors samt frigör områden i Södra hamnen för stadsbornas användning. Stadsmiljönämnden behandlar det reviderade planförslaget den 21 oktober.
Satamatunnelin asemakaava on valmis – tarkistettu kaavaehdotus päätöksentekoon17.10.2025 11:10:41 EEST | Tiedote
Länsisatamasta Länsiväylälle kulkevan Satamatunnelin asemakaavoitus on edennyt loppusuoralle. Tunneli parantaa Jätkäsaaren ja eteläisen Helsingin liikenteen sujuvuutta sekä vapauttaa Eteläsataman alueita kaupunkilaisten käyttöön. Kaupunkiympäristölautakunta käsittelee tarkistettua kaavaehdotusta 21. lokakuuta.
Kottby idrottspark blir en plats även för evenemang16.10.2025 11:13:33 EEST | Pressmeddelande
Helsingfors stad vill utveckla Kottby idrottspark till en ännu mångsidigare idrotts- och evenemangspark med både bättre idrottstjänster och möjlighet att ordna storevenemang. Just nu utarbetas en allmän plan för idrottsparken. Stadsborna kan dela med sig av sina tankar och idéer om utvecklingen av parken genom en webbenkät och en workshop.
Käpylän liikuntapuistoon koti myös tapahtumille16.10.2025 11:13:33 EEST | Tiedote
Käpylän liikuntapuistosta halutaan kehittää entistä monipuolisempi liikunta- ja tapahtumapuisto, jossa on parempien liikuntapalvelujen lisäksi mahdollista järjestää suurtapahtumia. Liikuntapuistolle tehdään parhaillaan yleissuunnitelmaa. Kaupunkilaiset voivat kertoa ajatuksiaan ja ideoitaan puiston kehittämisestä verkkokyselyssä ja työpajassa.
Helsingin kaupunkiympäristölautakunnan ympäristö- ja lupajaoston päätökset 9.10.20259.10.2025 18:37:33 EEST | Tiedote
Kokouksen päätöstiedote (yhteenveto tehdyistä päätöksistä) on julkaistu kaupungin verkkosivuilla: Päätöstiedote 9.10.2025 » Päätöstiedote näkyy verkkosivuilla siihen asti kun kokouksen pöytäkirja julkaistaan. Pöytäkirja korvaa valmistuttuaan päätöstiedotteen. Jaosto kokoontuu seuraavan kerran torstaina 23.10.2025.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom