Fault in the EstLink 2 Electricity Transmission Connection Between Finland and Estonia Located in the Submarine Cable
The electricity transmission connection between Finland and Estonia was disconnected on Wednesday, 25 December. The fault has been investigated in cooperation with the Estonian transmission system operator Elering and authorities. On Thursday, the fault was located in the submarine cable.
The EstLink 2 electricity transmission connection between Finland and Estonia disconnected from the grid after noon on Christmas Day. The Finnish and Estonian transmission system operators Fingrid and Elering immediately initiated fault investigation work together with the authorities, and the fault was located in the submarine cable on Thursday.
The electricity transmission connection is currently out of service. The failure of the cross-border electricity transmission link did not endanger the operation of the electricity system in Finland, the electricity system is functioning normally and electricity reliability is currently good, the electricity system is operating normally, and the electricity supply is currently sufficient. However, this situation may worsen if the weather conditions become colder for an extended period. However, during cold and windless periods, a failure of the EstLink 2 connection may make it more likely that the power situation will become tight.
Preparations for the repair work on the connection have begun. The repair work is estimated to take several months. We aim to provide a more precise schedule for the repair work on the EstLink 2 connection next week.
Authorities are investigating the sequence of events that led to the damage to the submarine cable.
Finland has electricity transmission connections to Estonia, Sweden, and Norway. EstLink 2 is the electricity transmission connection between Finland and Estonia, with a transmission capacity of 650 megawatts. The total length of the electricity transmission connection is 170 km, of which 145 km is submarine cable, 14 km is overhead line on the Finnish side, and 12 km is underground cable in Estonia.
For more information:
Arto Pahkin, Manager, Network Operations, Fingrid Oyj, tel. +358 30 395 4315
The emails are in the format: firstname.lastname@fingrid.fi
About Fingrid Oyj
Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.
Fingrid delivers. Responsibly.
www.fingrid.fi
Alternative languages
Subscribe to releases from Fingrid Oyj
Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fingrid Oyj
Fingridin talous- ja rahoitusjohtaja Jukka Metsälä irtisanoutunut28.4.2025 13:55:00 EEST | Tiedote
Fingrid Oyj:n talous- ja rahoitusjohtaja, DI, MBA Jukka Metsälä on irtisanoutunut yhtiön palveluksesta. Hänen viimeinen työpäivänsä yhtiössä on 31.7.2025. Metsälä siirtyy Fingridistä CableCrew Oy:n toimitusjohtajaksi 1.8.2025 alkaen.
Fingrid’s CFO Jukka Metsälä has resigned28.4.2025 13:55:00 EEST | Press release
Fingrid Oyj’s Chief Financial Officer, M.Sc., MBA Jukka Metsälä has given notice that he will be stepping down from his role in the company. His last day on the job is 31 July 2025. Metsälä will become Managing Director of CableCrew Oy as of 1 August 2025.
Fingrid-konsernin johdon katsaus 1.1.−31.3.202528.4.2025 13:48:12 EEST | Tiedote
Fingrid noudattaa arvopaperimarkkinalain mukaista puolivuosiraportointia ja julkistaa vuoden kolmen ja yhdeksän ensimmäisen kuukauden osalta johdon katsaukset, joissa esitetään yhtiön taloudellista ja muuta kehitystä kuvaavia keskeisiä tietoja. Johdon katsauksessa esitetyt tiedot koskevat Fingrid-konsernin kehitystä tammi-maaliskuussa 2025 ja vastaavalla jaksolla 2024, ellei toisin ole mainittu. Tässä esitetyt luvut ovat laadittu kansainvälisten tilinpäätösstandardien (International Financial Reporting Standards IFRS) mukaisesti. Johdon katsaus ei ole IAS 34 –standardin mukainen osavuosikatsaus. Luvut ovat tilintarkastamattomat. Fingridin kantaverkon siirtovarmuus oli korkea 100 (99,99991) prosenttia ja sähkön riittävyys oli hyvä. Lauhan talven vuoksi Suomen sähkön kulutus laski tammi-maaliskuussa 23,8 (24,6) terawattituntiin. Suomessa kulutetun sähkön päästöt alenivat. Yhtiö arvioi vuosien 2025–2028 bruttoinvestointien määrän olevan noin 1,7 miljardia euroa, josta on sidottu 623 miljo
Huolto- ja rakennustyöt vaikuttavat sähkön rajasiirtokapasiteettiin ja tuotannon enimmäismääriin länsirannikolla24.4.2025 12:53:11 EEST | Tiedote
Huolto- ja rakennustöistä aiheutuvat välttämättömät siirtokeskeytykset vaikuttavat tulevien kuukausien aikana Pohjois-Suomen ja Ruotsin välisten sähkön rajasiirtoyhteyksien siirtokapasiteettiin sekä länsirannikon tuotantolaitosten suurimpiin sallittuihin tuotantomääriin. Keskeytysten aikana rakennetaan uutta sekä ylläpidetään nykyistä kantaverkkoa. Keskeytyksiä vaativat työt ajoitetaan pääosin kesäkaudelle, jotta niiden vaikutukset sähköjärjestelmään ja Fingridin asiakkaisiin ovat mahdollisimman vähäisiä.
Puoliväliriihen kirjaukset tunnistavat siirtoverkkojen merkityksen kasvun mahdollistajana24.4.2025 10:26:13 EEST | Tiedote
Suomen hallitus on puoliväliriihen neuvottelujen tuloksena päättänyt huolehtia kantaverkkoyhtiö Fingridin tarvittavasta investointikyvystä. Tavoitteena on laajentaa nykyistä investointiohjelmaa ja siten tukea uusien teollisten investointien sijoittumista Suomeen.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom