Fingrid Oyj

Fault in the EstLink 2 Electricity Transmission Connection Between Finland and Estonia Located in the Submarine Cable

Share

The electricity transmission connection between Finland and Estonia was disconnected on Wednesday, 25 December. The fault has been investigated in cooperation with the Estonian transmission system operator Elering and authorities. On Thursday, the fault was located in the submarine cable.

The EstLink 2 electricity transmission connection between Finland and Estonia disconnected from the grid after noon on Christmas Day. The Finnish and Estonian transmission system operators Fingrid and Elering immediately initiated fault investigation work together with the authorities, and the fault was located in the submarine cable on Thursday. 

The electricity transmission connection is currently out of service. The failure of the cross-border electricity transmission link did not endanger the operation of the electricity system in Finland, the electricity system is functioning normally and electricity reliability is currently good, the electricity system is operating normally, and the electricity supply is currently sufficient. However, this situation may worsen if the weather conditions become colder for an extended period. However, during cold and windless periods, a failure of the EstLink 2 connection may make it more likely that the power situation will become tight. 

Preparations for the repair work on the connection have begun. The repair work is estimated to take several months. We aim to provide a more precise schedule for the repair work on the EstLink 2 connection next week. 

Authorities are investigating the sequence of events that led to the damage to the submarine cable. 

Finland has electricity transmission connections to Estonia, Sweden, and Norway. EstLink 2 is the electricity transmission connection between Finland and Estonia, with a transmission capacity of 650 megawatts. The total length of the electricity transmission connection is 170 km, of which 145 km is submarine cable, 14 km is overhead line on the Finnish side, and 12 km is underground cable in Estonia. 

For more information: 

Arto Pahkin, Manager, Network Operations, Fingrid Oyj, tel. +358 30 395 4315 
The emails are in the format: firstname.lastname@fingrid.fi 

About Fingrid Oyj

Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.

Fingrid delivers. Responsibly.
www.fingrid.fi

Alternative languages

Subscribe to releases from Fingrid Oyj

Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from Fingrid Oyj

Viidentoista minuutin vuorokausimarkkinoiden käyttöönottopäivämääräksi vahvistettu 30.9.202512.9.2025 11:14:00 EEST | Tiedote

Eurooppalaisten kantaverkkoyhtiöiden ja sähköpörssien yhteinen ohjausryhmä MCSC (Market Coupling Steering Committee) on vahvistanut viidentoista minuutin (ns. vartin) vuorokausimarkkinoiden käyttöönottopäivämääräksi keväällä ilmoitetun mukaisesti 30.9.2025, energian toimituspäivälle 1.10.2025. Kaikkien osapuolten valmius käyttöönottoon on varmistettu kattavilla testeillä. Linkki MCSC:n tiedotteeseen > Lisätietoja Marja Eronen, Fingrid Oyj, puh. 030 395 4457 Sähköpostiosoitteemme ovat muodossa etunimi.sukunimi@fingrid.fi. Aiempi tiedotteemme aiheesta >

Uusi kahden virtapiirin siirtolinja tukee Etelä-Suomen uutta sähkönkulutusta5.9.2025 11:31:17 EEST | Tiedote

Fingrid rakentaa Alajärveltä Hausjärvelle kantaverkon järeän kahden virtapiirin pääsiirtolinjan, joka edistää länsirannikolle voimakkaasti keskittyneen tuulivoimatuotannon siirtämistä kulutukseen. Vuosina 2028–2029 valmistuva 400 kilovoltin siirtoyhteys on yksi Fingridin tärkeimmistä investointihankkeista ja osa Lakeuslinjaa. Se mahdollistaa merkittävästi uutta sähkönkulutusta Etelä-Suomessa, helpottaa siirtokeskeytyksiä ja parantaa koko sähköjärjestelmän käyttövarmuutta. Hankkeen investointikustannukset ovat yli 160 miljoonaa euroa.

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye