Fingrid Oyj

Fault in the EstLink 2 Electricity Transmission Connection Between Finland and Estonia Located in the Submarine Cable

Share

The electricity transmission connection between Finland and Estonia was disconnected on Wednesday, 25 December. The fault has been investigated in cooperation with the Estonian transmission system operator Elering and authorities. On Thursday, the fault was located in the submarine cable.

The EstLink 2 electricity transmission connection between Finland and Estonia disconnected from the grid after noon on Christmas Day. The Finnish and Estonian transmission system operators Fingrid and Elering immediately initiated fault investigation work together with the authorities, and the fault was located in the submarine cable on Thursday. 

The electricity transmission connection is currently out of service. The failure of the cross-border electricity transmission link did not endanger the operation of the electricity system in Finland, the electricity system is functioning normally and electricity reliability is currently good, the electricity system is operating normally, and the electricity supply is currently sufficient. However, this situation may worsen if the weather conditions become colder for an extended period. However, during cold and windless periods, a failure of the EstLink 2 connection may make it more likely that the power situation will become tight. 

Preparations for the repair work on the connection have begun. The repair work is estimated to take several months. We aim to provide a more precise schedule for the repair work on the EstLink 2 connection next week. 

Authorities are investigating the sequence of events that led to the damage to the submarine cable. 

Finland has electricity transmission connections to Estonia, Sweden, and Norway. EstLink 2 is the electricity transmission connection between Finland and Estonia, with a transmission capacity of 650 megawatts. The total length of the electricity transmission connection is 170 km, of which 145 km is submarine cable, 14 km is overhead line on the Finnish side, and 12 km is underground cable in Estonia. 

For more information: 

Arto Pahkin, Manager, Network Operations, Fingrid Oyj, tel. +358 30 395 4315 
The emails are in the format: firstname.lastname@fingrid.fi 

About Fingrid Oyj

Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.

Fingrid delivers. Responsibly.
www.fingrid.fi

Alternative languages

Subscribe to releases from Fingrid Oyj

Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from Fingrid Oyj

Fingridin sähköjärjestelmävisio 2040: Suomi kohti kilpailukykyistä ja sähköistynyttä tulevaisuutta9.10.2025 15:15:55 EEST | Tiedote

Fingrid on julkaissut sähköjärjestelmävision sähköistyneelle ja kilpailukykyiselle Suomelle vuonna 2040. Visio osoittaa, että Suomella on kaikki edellytykset houkutella sähköintensiivistä teollisuutta ja saada merkittävä määrä uusia investointeja sähkön kulutukseen ja tuotantoon. Kasvun mahdollistamiseksi tarvitaan vahvistuksia kantaverkkoon ja uusia keinoja sen tehokkaaseen hyödyntämiseen yhdessä asiakkaiden kanssa, sekä investoinnit mahdollistavaa vakaata ja ennakoitavaa toimintaympäristöä. Esittelemme sähköjärjestelmävision tuloksia webinaarissa 23.10.

Elsystemet utvidgas och förändras, vilket ökar kostnaderna – Fingrid höjer sina stamnätsavgifter i början av nästa år25.9.2025 15:00:00 EEST | Pressmeddelande

Stamnätsbolaget Fingrid kommer att höja avgifterna för stamnätstjänster med 8 % i början av 2026. Orsaken till höjningen är ett omfattande proaktivt investeringsprogram för framtida kundbehov samt ökade kostnader i det växande elsystemet. Även anslutningsavgifterna till stamnätet höjs för att motsvara kostnadsutvecklingen.

The expanding and changing electricity system increases costs – Fingrid to raise grid service fees at the start of the year25.9.2025 15:00:00 EEST | Press release

The transmission system operator Fingrid will raise grid service fees by 8% at the start of 2026. Key factors behind the increase are a substantial investment programme that anticipates future customer needs and the rising costs of the expanding electricity system. Grid connection fees will also be increased to reflect cost developments.

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye