Repair work on the electricity transmission link between Finland and Estonia to begin in May
The actual repair work on the EstLink 2 electricity transmission link between Finland and Estonia, which was damaged on Christmas Day 2024, will start in May. The electricity transmission link is expected to return to commercial use once the repair work is completed in July.

The actual repair work on the electricity transmission connection between Finland and Estonia will begin in May. The repair work is expected to take two months, and the connection is expected to return to commercial use on July 15, 2025.
Preliminary work has already been carried out on the EstLink 2 submarine cable connection during February and April. The damaged section of the cable was excavated and cut out at sea for further examination, and the remaining cable sections were tested for integrity. The preliminary work aimed to reduce the risks associated with the actual repair work and helped to refine the details of the actual repair plan.
“A new cable is being installed on the seabed to replace the existing one over a distance of approximately one kilometer. Implementing such extensive repair work has required detailed planning and necessitates a specially equipped vessel for the task. The repair work has been planned and prepared since January in close cooperation with Nexans, the company carrying out the work”, says unit manager Kimmo Nepola.
The cable connection will be ready to return to commercial use once the repair work is completed and the tests ensuring the functionality of the cable connection have been successfully completed. The return of the EstLink 2 connection to commercial use will be announced once the repair work is completed.
For more information:
Kimmo Nepola, Unit Manager, Fingrid, tel. +358 30 395 4221
Emails are in the format firstname.lastname@fingrid.fi
About Fingrid Oyj
Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.
Fingrid delivers. Responsibly.
www.fingrid.fi
Alternative languages
Subscribe to releases from Fingrid Oyj
Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fingrid Oyj
Fingridin talous- ja rahoitusjohtaja Jukka Metsälä irtisanoutunut28.4.2025 13:55:00 EEST | Tiedote
Fingrid Oyj:n talous- ja rahoitusjohtaja, DI, MBA Jukka Metsälä on irtisanoutunut yhtiön palveluksesta. Hänen viimeinen työpäivänsä yhtiössä on 31.7.2025. Metsälä siirtyy Fingridistä CableCrew Oy:n toimitusjohtajaksi 1.8.2025 alkaen.
Fingrid’s CFO Jukka Metsälä has resigned28.4.2025 13:55:00 EEST | Press release
Fingrid Oyj’s Chief Financial Officer, M.Sc., MBA Jukka Metsälä has given notice that he will be stepping down from his role in the company. His last day on the job is 31 July 2025. Metsälä will become Managing Director of CableCrew Oy as of 1 August 2025.
Fingrid-konsernin johdon katsaus 1.1.−31.3.202528.4.2025 13:48:12 EEST | Tiedote
Fingrid noudattaa arvopaperimarkkinalain mukaista puolivuosiraportointia ja julkistaa vuoden kolmen ja yhdeksän ensimmäisen kuukauden osalta johdon katsaukset, joissa esitetään yhtiön taloudellista ja muuta kehitystä kuvaavia keskeisiä tietoja. Johdon katsauksessa esitetyt tiedot koskevat Fingrid-konsernin kehitystä tammi-maaliskuussa 2025 ja vastaavalla jaksolla 2024, ellei toisin ole mainittu. Tässä esitetyt luvut ovat laadittu kansainvälisten tilinpäätösstandardien (International Financial Reporting Standards IFRS) mukaisesti. Johdon katsaus ei ole IAS 34 –standardin mukainen osavuosikatsaus. Luvut ovat tilintarkastamattomat. Fingridin kantaverkon siirtovarmuus oli korkea 100 (99,99991) prosenttia ja sähkön riittävyys oli hyvä. Lauhan talven vuoksi Suomen sähkön kulutus laski tammi-maaliskuussa 23,8 (24,6) terawattituntiin. Suomessa kulutetun sähkön päästöt alenivat. Yhtiö arvioi vuosien 2025–2028 bruttoinvestointien määrän olevan noin 1,7 miljardia euroa, josta on sidottu 623 miljo
Huolto- ja rakennustyöt vaikuttavat sähkön rajasiirtokapasiteettiin ja tuotannon enimmäismääriin länsirannikolla24.4.2025 12:53:11 EEST | Tiedote
Huolto- ja rakennustöistä aiheutuvat välttämättömät siirtokeskeytykset vaikuttavat tulevien kuukausien aikana Pohjois-Suomen ja Ruotsin välisten sähkön rajasiirtoyhteyksien siirtokapasiteettiin sekä länsirannikon tuotantolaitosten suurimpiin sallittuihin tuotantomääriin. Keskeytysten aikana rakennetaan uutta sekä ylläpidetään nykyistä kantaverkkoa. Keskeytyksiä vaativat työt ajoitetaan pääosin kesäkaudelle, jotta niiden vaikutukset sähköjärjestelmään ja Fingridin asiakkaisiin ovat mahdollisimman vähäisiä.
Puoliväliriihen kirjaukset tunnistavat siirtoverkkojen merkityksen kasvun mahdollistajana24.4.2025 10:26:13 EEST | Tiedote
Suomen hallitus on puoliväliriihen neuvottelujen tuloksena päättänyt huolehtia kantaverkkoyhtiö Fingridin tarvittavasta investointikyvystä. Tavoitteena on laajentaa nykyistä investointiohjelmaa ja siten tukea uusien teollisten investointien sijoittumista Suomeen.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom