EstLink 2 electricity transmission link returns to commercial use

Share

The repair work on the electricity transmission link between Finland and Estonia has been completed, and the link is expected to return to commercial use on Friday, June 20th. The transmission link has been out of service since December.

Fingrid

The repair work on the EstLink 2 electricity transmission link has been completed, and the link is expected to return to commercial use on Friday. The actual repair work has been carried out at sea since May.

The repair work has proceeded as planned and in close cooperation with various parties. During the repair work, the damaged submarine cable was replaced with a new cable over a distance of approximately one kilometer. Excellent cooperation with the authorities has enabled the repair work to be carried out safely in a busy maritime area.

"The tests related to the commissioning of the cable began on Tuesday evening and have continued without issues throughout the night," says unit manager Kimmo Nepola. The cable will be returned to commercial use after a successful test period.

EstLink 2 was damaged on Christmas Day and has been out of service since then. The damage to the transmission link has not affected the functioning of the electricity system in Finland, but the fault temporarily reduced the electricity transmission capacity between the countries by 650 megawatts.

For more information:  
Kimmo Nepola, Unit Manager, Fingrid, tel. +358 30 395 4221  
Emails are in the format firstname.lastname@fingrid.fi


About Fingrid Oyj

Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.

Fingrid delivers. Responsibly.
www.fingrid.fi

Alternative languages

Subscribe to releases from Fingrid Oyj

Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from Fingrid Oyj

Fingrid parantaa liityntäsuunnittelua ja tiedonkulkua13.6.2025 14:57:08 EEST | Tiedote

Fingrid ottaa käyttöön uuden menettelyn verkon liityntäsuunnitelmien tiedonkulun parantamiseksi. Menettelyn tavoitteena on parantaa verkon liitettävyyttä. Fingrid kerää jatkossa tiedon kaikista suunniteltavista verkon liitynnöistä, jotta liitynnöistä sopimiseen on yhteiset, reilut periaatteet. Menettely otetaan käyttöön aluksi eteläisen Suomen alueella ja se koskee alueen jakeluverkkoyhtiöiden sekä suoraan kantaverkkoon liittyneen teollisuuden suuria kulutus- sekä sähkövarastoliityntöjä.

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye