Main grid development plan: investments in electricity transmission links continue to grow
4.9.2025 09:57:49 EEST | Fingrid Oyj | Press release
Fingrid has published its main grid development plan for the period 2026–2035. The plan aims to enable industrial investments in clean electricity and the attainment of climate targets. The alternative scenarios included in the development plan will also allow Fingrid to respond to changing customer needs.

Finland’s main grid is currently being reinforced more than ever before, and at an accelerating pace: investments will reach EUR 1.7 billion in the period 2025–2028. A huge increase in planned customer projects shows that clean, secure and affordable electricity is attracting electricity-intensive industry to Finland.
The projects presented in the draft development plan are based on Fingrid's forecasts of customer needs, which have been used to identify development needs, and particularly in main grid trunk connections. The plan also presents transmission line projects that will serve customer needs and whose zoning and permit processes have progressed. The timeline for reinforcing the main grid may change as customer needs and forecasts are updated.
Fingrid is also seeking to make more efficient use of the existing grid through a variety of measures aimed at increasing its transmission capacity, and with the aid of customer flexibility, but without compromising security of supply. In addition, the conditional connection agreement introduced by Fingrid earlier this summer brings certainty to the grid connections of large industrial projects and thus promotes investment decision-making.
The main grid’s key development needs
The main grid development plan covers not only its key trunk connections, but also reinforcements at regional level. The development plan has identified significant needs for reinforcement in north–south and west–south transmission links, which will be implemented with the aid of new transmission lines and compensation solutions.
About two-thirds of the country’s electricity consumption is located in Southern Finland, to the south of Tampere. Several transmission connections will be completed by the end of the decade to reinforce transmission lines in the region.
At the moment, it is only possible to connect new electricity production and consumption to Eastern Finland in a decentralised manner. In addition to the transmission line projects that are already underway, Fingrid is actively monitoring the situation in Eastern Finland and preparing to launch the necessary grid reinforcements as customer projects progress. Fingrid is also launching an environmental impact assessment in preparation for the implementation of an eastbound 400-kilovolt transmission link.
Fingrid's aim is to develop the main grid as a means of ensuring that customers have the opportunity for growth. In addition to grid investments, project location steering and the implementation of flexible, hybrid connections can facilitate the connection of customer projects to the grid. Effective development of the main grid also requires adequate financing and smooth permit processes. For example, it currently takes almost two years to obtain expropriation permits for transmission lines, which makes it difficult to meet customers' rapidly changing needs.
Send us your feedback
The draft main grid development plan is available on Fingrid’s website (in Finnish) , where you will also find a link for sharing feedback. The development plan will be presented to customers at a seminar on 29 September, and feedback can be given until 3 October at palautteet@fingrid.fi. After that, the plan will be updated and the final development plan will be published in late 2025.
Further information:
Jussi Jyrinsalo, Senior Vice President, Transmission System Services and Grid Planning, Fingrid Oyj, tel. +358 30 3955118, e-mail addresses: forename@surname@fingrid.fi
Term explanation: What is the main grid development plan?
The main grid development plan presents the development needs of the main grid for the next ten years. The preparation of the grid development plan is subject to the provisions of the Electricity Market Act, and the plan is updated every two years. Fingrid will first publish a draft development plan for stakeholder comments. The feedback received while the draft is being circulated for comments will be assessed, and Fingrid will then publish the final grid development plan after making any necessary revisions.
About Fingrid Oyj
Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.
Fingrid delivers. Responsibly.
www.fingrid.fi
Alternative languages
Subscribe to releases from Fingrid Oyj
Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fingrid Oyj
Uudistunut Verkkokiikari-karttapalvelu tarjoaa tietoa kantaverkon liittymismahdollisuuksista14.4.2026 13:54:30 EEST | Tiedote
Kantaverkon liittymismahdollisuuksia esittelevä Verkkokiikari-karttapalvelu on uudistunut. Verkkokiikari tarjoaa nyt tietoa sähkön tuotannon ja kulutuksen liittymismahdollisuuksien ohella myös sähkövarastojen vapaista aluekohtaisista kapasiteeteista sekä aluekohtaisista rajoitteista. Ajantasainen, yhtenäinen tieto kantaverkon liittymismahdollisuuksista tukee eri osapuolien suunnittelutyötä sekä verkon ennakoivaa kehitystä.
Kuukausitason (M1) kapasiteettilaskenta käyttöön Pohjoismaissa13.4.2026 14:08:53 EEST | Tiedote
Pohjoismaiset kantaverkkoyhtiöt Fingrid, Svenska kraftnät, Statnett ja Energinet ovat ottaneet 8.4.2026 käyttöön pitkän aikavälin kapasiteetinlaskennan kuukausitasolla (M-1 Long-Term Capacity Calculation). Käyttöönoton myötä Flow-based -menetelmällä lasketut siirtokapasiteetit julkaistaan edellisen kuukauden loppupuolella seuraavalle kuukaudelle eli toukokuulle kapasiteetit julkaistaan huhtikuun lopulla.
Webinaari pitkän aikavälin siirtokapasiteetin osittamismenetelmän julkisen kuulemisen tuloksista10.4.2026 09:51:06 EEST | Tiedote
Elering ja Fingrid kutsuvat markkinaosapuolet yhteiseen webinaariin, jossa esitellään viimeisimmän julkisen kuulemisen tulokset koskien pitkän aikavälin siirtokapasiteetin jakamista koskevaa yhteistä osittamismenetelmää (FCA GL, artikla 16) sekä siihen ehdotettuja muutoksia. Webinaarissa käsitellään myös FI–EE FTR-sopimusten enimmäismäärien ehdotettuja muutoksia. Webinaarissa kantaverkkoyhtiöt esittelevät ehdotuksen taustat ja perustelut, yhteenvedon markkinaosapuolilta saadusta palautteesta sekä lopullisen muutosesityksen, joka on toimitettu regulaattoreille. Webinaarin ajankohta: 21.4.2026 klo 13.00–14.00 (EET) Linkki webinaariin. Webinaari pidetään englanniksi. Tervetuloa mukaan! Lisätietoja: Marina Nordström, erikoisasiantuntija, Fingrid Oyj, puh 030 3954 284 Airi Noor, Elering AS Fingridin sähköpostiosoitteet muotoa etunimi.sukunimi@fingrid.fi Kuuleminen muutoksesta pitkän aikavälin siirtokapasiteetin osittamismenetelmään FI–EE-rajalla (26.1.2026) [fingrid.fi] Linkki kuulemiseen E
Christoffer Nyberg avgår ur Fingrids styrelse9.4.2026 16:51:38 EEST | Pressmeddelande
Christoffer Nyberg har meddelat att han avgår ur Fingrids styrelse. Hans utträde ur styrelsen är relaterat till att Ömsesidiga Pensionsförsäkringsbolaget Ilmarinen har sålt cirka 20 procent av sin ägarandel i Fingrid till finska staten och OP Pohjola Kantaverkko Holding Ky. Nyberg är Senior Portfolio Manager vid Ömsesidiga Pensionsförsäkringsbolaget Ilmarinen. Fingrids styrelse är fortsatt beslutsför efter avgången. Mer information: Marina Louhija, styrelsens sekreterare, direktör, juridiska ärenden och hållbarhet, Fingrid Oyj, tfn 040 519 0627
Christoffer Nyberg luopuu Fingridin hallituksen jäsenyydestä9.4.2026 16:51:38 EEST | Tiedote
Christoffer Nyberg on ilmoittanut luopuvansa Fingridin hallituksen jäsenyydestä. Jäsenyydestä luopuminen liittyy siihen, että Keskinäinen Eläkevakuutusyhtiö Ilmarinen on myynyt noin 20 prosentin omistusosuutensa Fingridistä Suomen valtiolle ja OP Pohjola Kantaverkko Holding Ky:lle. Nyberg toimii Keskinäinen Eläkevakuutusyhtiö Ilmarisen vanhempana salkunhoitajana. Fingridin hallitus säilyy eron jälkeen päätösvaltaisena. Lisätietoja: Marina Louhija, Fingridin hallituksen sihteeri, johtaja, laki- ja vastuullisuusasiat, Fingrid Oyj, puh. 040 519 0627
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom