Permission to increase the power of Olkiluoto 3
Once authorized, TVO will gradually increase the power of the reactor from 60% to its full thermal power of 4300 megawatts. During this increase, the plant provider and TVO will ensure that the plant functions as planned also at these power levels. STUK monitors the power increase on site.
According to Essi Vanhanen, Project Manager responsible for regulatory control of OL3 at STUK, the commissioning tests carried thus far and related reports have shown that Finland's newest nuclear plant unit has operated safely and the reactor power can be increased further according to commissioning testing plans.
The commissioning tests were delayed when detached parts of the steam guide plates were found in the turbine reheater in May. After repairs and inspections, TVO submitted a report to STUK, stating that the incident did not compromise nuclear safety and that commissioning of the plant can be safely continued.
When the reactor power was increased after the repair shutdown, TVO and the plant supplier discovered that the plant's operational automation software still needed to be updated. TVO submitted a report on the matter to STUK and after the update, TVO and the plant supplier continued the commissioning as planned.
More detailed information on STUK’s surveillance observations can be found from the “Surveillance news” section of the stuk.fi website.
Keywords
Contacts
Project Manager Essi Vanhanen, tel. +358 9 7598 8242
Media contacts
Tel:+358(10)8504761Links
About Säteilyturvakeskus (STUK)
Subscribe to releases from Säteilyturvakeskus (STUK)
Subscribe to all the latest releases from Säteilyturvakeskus (STUK) by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Säteilyturvakeskus (STUK)
Fem länders myndigheter utvärderar det finländska kärnanläggningskonceptets säkerhet19.1.2026 10:05:03 EET | Pressmeddelande
Strålsäkerhetscentralen koordinerar den internationella säkerhetsbedömningen av en finländsk småskalig modulär reaktor. I arbetet utreds hur samarbete kan underlätta bedömningen av nya anläggningar.
Viiden maan viranomaiset arvioivat suomalaisen ydinvoimalaitoskonseptin turvallisuutta19.1.2026 10:05:03 EET | Tiedote
Säteilyturvakeskus koordinoi suomalaisen pienydinreaktorin kansainvälistä turvallisuusarviointia. Työssä selvitetään, miten yhteistyö voisi helpottaa uusien laitosten arviointityötä.
Authorities from five countries assess the safety of a Finnish nuclear power plant concept19.1.2026 10:05:03 EET | Press release
The Radiation and Nuclear Safety Authority (STUK) is coordinating the international safety assessment of a Finnish small modular reactor. The project examines how cooperation could facilitate the evaluation of new nuclear facilities.
STUK:s luftinsamlare fångade radioaktivt brom18.12.2025 11:12:26 EET | Pressmeddelande
Strålsäkerhetscentralen upptäckte en ofarlig liten mängd radioaktivt brom i utomhusluften i Vanda i ett prov som samlades in den 11-12 december. Brom kan härstamma till exempel från en spårämnesmätning som har utförts korrekt i en industrifacilitet, där en radioaktiv isotop av brom har använts som spårämne.
STUKin ilmankerääjään tarttui radioaktiivsta bromia18.12.2025 11:12:26 EET | Tiedote
Säteilyturvakeskus havaitsi Vantaan ulkoilmassa haitattoman pienen määrän radioaktiivista bromia joulukuun 11.-12. kerätyssä näytteessä. Bromi voi olla peräisin esimerkiksi teollisuuslaitoksessa asiallisesti tehdystä kokeesta, jossa bromin radioaktiivista isotooppia on käytetty merkkiaineena.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom
