The Radiation and Nuclear Safety Authority (STUK) has granted a fuel loading permit for Teollisuuden Voima Oyj’s (TVO) Olkiluoto 3 nuclear power plant unit (OL3) on 26 March 2021.

STUK states in its fuel loading permit that OL3 meets the safety requirements set for it and its security and emergency arrangements and procedures are sufficient in order to load nuclear fuel in the reactor. STUK also states that the control necessary to prevent the proliferation of nuclear weapons has been appropriately arranged and that the nuclear facility licensee has arranged, in the manner provided, indemnification regarding liability in the event of nuclear damage.

Project Manager Essi Vanhanen from STUK states that when the fuel loading begins, OL3 will be regarded as an operating nuclear power plant and STUK’s oversight will continue as oversight of a nuclear power plant in use. TVO, as the licensee, is responsible for ensuring that the plant is safe and used in accordance with the safety requirements.

The fuel loading is followed by a commissioning phase lasting several months during which TVO will continue to test the plant. There is a number of tests that require fuel to be loaded in the reactor to show that the systems work correctly. TVO has planned that regular electricity generation will start in February 2022.

According to Project Manager Essi Vanhanen, STUK oversees the commissioning phase closely and TVO needs an authorization from STUK before advancing from one commissioning phase to another.







Keywords

Contacts

Project Manager Essi Vanhanen, tel. +358 9 759 88 242


Deputy Director Tomi Routamo, tel. +358 9 759 88 577

Documents

Links

About Säteilyturvakeskus (STUK)

Säteilyturvakeskus (STUK)
Säteilyturvakeskus (STUK)
Jokiniemenkuja 1
01370 Vantaa

Mediapalvelu: 010 850 4761http://www.stuk.fi

Säteilyturvakeskus (STUK) on sosiaali- ja terveysministeriön hallinnonalan viranomainen, joka valvoo säteily- ja ydinturvallisuutta Suomessa. Tehtävämme on ihmisten, yhteiskunnan, ympäristön ja tulevien sukupolvien suojelu säteilyn haitallisilta vaikutuksilta. 

Subscribe to releases from Säteilyturvakeskus (STUK)

Subscribe to all the latest releases from Säteilyturvakeskus (STUK) by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from Säteilyturvakeskus (STUK)

STUK publicerade en forskningsrapport om kärnsäkerhetssamarbete som började när Sovjetunionen kollapsade och slutade när det ryska anfallskriget började4.11.2025 14:08:28 EET | Pressmeddelande

Strålsäkerhetscentralen hjälpte ryssarna att förbättra säkerheten vid sina kärnkraftverk i trettio års tid från början av 1990-talet. Samarbetet upphörde när Ryssland anföll Ukraina. Historieforskaren Petri Paju har skrivit om erfarenheterna av samarbetet i en forskningsrapport som Strålsäkerhetscentralen publicerat.

STUK published a research report on nuclear safety cooperation that began when Soviet Union collapsed and ended in Russian war of aggression.4.11.2025 14:08:28 EET | Press release

The Radiation and Nuclear Safety Authority helped Russia improve the safety of their nuclear power plants for thirty years from the beginning of the 1990s. This cooperation ended following Russia’s invasion of Ukraine. History researcher Petri Paju has reported on the experiences of this cooperation in a research report published by the Radiation and Nuclear Safety Authority.

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye