The design of Dance House Helsinki is starting to take shape

Jaa
The design of Dance House Helsinki, which is built in connection to Cable Factory, is starting to take shape as the actual construction phase is approaching. Space utilization has been enhanced by moving the dance rehearsal studio to the old factory building. The height of the new building has also been lowered. The far end of the Cable Factory's courtyard is left in its original state while the entrance to the new lobby is made bigger. In addition, a “bazaar” will be opened at Cable Factory.

The project plan for the Dance House was announced a year ago in March 2017. During the past year, the plan was complemented architectonically, and during the plan process, the plan has been commented on several stages by both the authorities, neighbours, dance operators and Cable Factory tenants.

Feedback was taken into account in the updated plan

The feedback presented during the plan process has been taken into account in the updated plan announced by Kiinteistö Oy Kaapelitalo and Dance House Helsinki on Tuesday, April 10, 2018. The changes will also protect the architectural tradition of the old factory building more clearly than before. Changes in the use of space have been made so that the space of the house has not been substantially changed.

- Challenges and compromises are commonplace in such projects, but we have had a good and interactive way to go about it. Changes in the plan have been made under the conditions of the dance house, so we have not had to compromise on our intended operations, says Hanna-Mari Peltomäki, the executive director of Dance House Association.

Most important changes

The most important change in the updated plan is to move the dance rehearsal studio from the new building into the old factory building. This has enabled us to have more green space on the north side of the building. At the same time, the height of the new building has been lowered. The move of the rehearsal studio will also make it possible to make better use of the extra space in the building.

Another major change is that the western end of Cable Factory's inner yard is no longer covered. The part of the inner yard that is on the Dance House side, will be covered and serve as a new lobby area. From this heated lobby, there is access to all the Cable Factory’s stairs through a new accessible tunnel. At the same time, the Ruoholahti entrance to the lobby is widened. This way, the view towards the east will remain bright and spacious even in the future.

In addition, with the construction of the dance house, the old factory building is renovated into a “bazaar”. It will be located in the existing Ceramic Center Septaria’s premises and the spaces above it. Cable Factory invites all the tenants and he residents in the neighbourhood to come together and brainstorm on the new bazaar concept. Cable Factory hopes that the works of its tenants could be at display in the marketplace – everything from visual arts to design and ceramics.

- Thanks to these changes, the cultural centre will become an even better place to design, to make and to experience culture in all its various forms, says Kai Huotari, Managing Director of Kiinteistö Oy Kaapelitalo.

Co-operation has been fruitful

Since the start of the project plan two years ago, construction costs have increased significantly in the Helsinki Metropolitan Area, which has posed challenges to the project. However, the updated plans have remained in the original 34.8 million euro cost framework thanks to excellent co-operation.

- Our long and seamless cooperation with the management and the architects has been fruitful. We have been able to find solutions to difficult challenges that satisfy everyone, Huotari says.

The town plan for the Dance House will go through a second round in the board in April, and in the city council in May. If the plan will gain legal force, the construction work will start in summer 2018. The house is due to be completed in early autumn 2020.

Avainsanat

Yhteyshenkilöt

Hanna-Mari Peltomäki, Dance House Association, hanna-mari.peltomaki@tanssintalo.fi, tel. +358 44 513 1069


Kai Huotari, Kiinteistö Oy Kaapelitalo, kai.huotari@kaapelitehdas.fi, tel. +358 50 384 1557

Kuvat

Linkit

Tietoja julkaisijasta

Kiinteistö Oy Kaapelitalo
Kiinteistö Oy Kaapelitalo
Tallberginkatu 1 C 15
00180 HELSINKI

info@kaapelitehdas.fi, 09 4763 8300http://www.kaapelitehdas.fi

Kaapelitehtaan, N10:n ja Suvilahden kulttuurikeskuksia hallinnoi Helsingin kaupungin omistama Kiinteistö Oy Kaapelitalo, joka omistaa, peruskorjaa ja vuokraa vanhoja teollisuuskiinteistöjä kulttuurikäyttöön.

Kaapelitehdas on Suomen suurimpia kulttuurikeskuksia, jossa toimii mm. 3 museota, 10 galleriaa, ravintoloita ja kahviloita, tanssiteattereita, taidekouluja sekä taiteilijoita, bändejä ja luovien alojen yrityksiä. Kaapelitehtaan yhteydessä toimii myös Tanssin talo.

Suvilahden entisen sähkövoimalan ja kaasulaitoksen alueeseen kuuluu 9 rakennusta, 2 kaasukelloa sekä 2,5 hehtaaria piha-aluetta. Suvilahden ovat ottaneet omakseen monenlaiset kulttuuritoimijat kirjailijoista esittäviin taiteisiin ja uudesta sirkuksesta valokuvaajiin.

N10:n kiinteistö Vallilassa on lääkeyhtiö Orionin entinen pääkonttori ja lääketehdas. Viidessä toimistokerroksessa ja kahdessa kellarikerroksessa toimii noin 250 lähinnä kulttuuri- ja taidealan vuokralaista.

www.kaapelitehdas.fi

www.suvilahti.fi

www.n10.fi

Tilaa tiedotteet sähköpostiisi

Haluatko tietää asioista ensimmäisten joukossa? Kun tilaat tiedotteemme, saat ne sähköpostiisi välittömästi julkaisuhetkellä. Tilauksen voit halutessasi perua milloin tahansa.

Lue lisää julkaisijalta Kiinteistö Oy Kaapelitalo

HiddenA line styled icon from Orion Icon Library.Eye