Maintenance and construction work will limit electricity transmission capacity between Sweden and Finland in the summer
The transmission capacity of the cross-border electricity transmission connection between Northern Finland and Sweden will be lower than usual in the summer due to maintenance and construction work on transmission lines. The modifications and measurements carried out during the outage ensure the operational reliability and safety of the cross-border transmission connection.

Work to improve the reliability and operational safety of the cross-border transmission connection will be carried out on transmission lines in northern Sweden in early summer, which is why part of the cross-border electricity transmission connection between Finland and Sweden will be out of service. During the limitation period, the transmission capacity of the connection from Finland to Sweden will be 300 megawatts (usually 1100 megawatts) and the transmission capacity of the connection from Sweden to Finland will be 200 megawatts (usually 1200 megawatts). The estimated duration of the interruptions is just over three weeks.
A similar restriction will be repeated in July and August, when the construction work of the Aurora Line transmission line will continue with an interruption of approximately four weeks. The Aurora Line is a new cross-border transmission connection implemented jointly by Fingrid and Svenska kraftnät, which, when completed in 2025, will significantly increase transmission capacity between Finland and Sweden. The Aurora Line transmission line is 380 kilometres long and runs from the Pyhänselkä substation in Muhos all the way to Messaure in Sweden.
The construction of the first phase of the Aurora Line began in autumn 2022 in Finland. In addition to increasing transmission capacity, Aurora Line will improve the security of electricity supply and the resilience of the electricity system not only in Finland and Sweden, but also more widely in the entire Baltic Sea region.
Restrictions on cross-border transmission connections increase sensitivity to fluctuations in electricity prices
During border capacity limitations, sensitivity to fluctuations in electricity prices increases. In particular, price fluctuations may be greater than usual in situations where there are simultaneously several influencing factors, such as low or high wind power production, disturbances in power plants or disturbances in other transmission connections.
In addition, there will be several outages in Ostrobothnia during the summer because of construction work strengthening the main grid , during which the maximum production of wind power will have to be limited regionally by a maximum of 2,000 megawatts due to system security.
"Cross-border transmission connections to Sweden and Estonia are very important for the functioning of the electricity market and the system security of the Finnish electricity system. At the moment, the main grid is being built at a rapid pace in Finland and Sweden, which also causes restrictions and interruptions in electricity transmission. Fingrid and Svenska kraftnät work closely together on both sides of the border to ensure that necessary outages cause as little inconvenience as possible," says Tuomas Rauhala, Director of Power System Operations at Fingrid.
Additional information:
Senior Advisor Timo Kaukonen, phone +358 40 545 2124
Unit Manager Mikko Piironen, phone +358 50 599 0141
Email addresses are in the format etunimi.sukunimi@fingrid.fi
Keywords
About Fingrid Oyj
Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.
Fingrid delivers. Responsibly.
www.fingrid.fi
Alternative languages
Subscribe to releases from Fingrid Oyj
Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Fingrid Oyj
Suuntaajavaltaisen sähköjärjestelmän alueellista toimintaa siirtokeskeytystilanteessa todennettiin onnistuneella verkkokokeella15.5.2025 10:04:08 EEST | Tiedote
Fingrid toteutti 7.5. länsirannikolla verkkokokeen, jolla todennettiin sähköjärjestelmän toiminnan turvaavien toimenpiteiden oikeaa mitoitusta ja kohdentamista. Lisäksi koe mahdollisti uudenlaisen suojausjärjestelmän toiminnallisen testauksen todellisessa käyttötilanteessa. Verkkokoe oli onnistunut, eikä aiheuttanut häiriöitä asiakkaille.
Viidentoista minuutin vuorokausimarkkinoiden käyttöönotto viivästyy14.5.2025 13:07:09 EEST | Tiedote
Eurooppalaisten kantaverkkoyhtiöiden ja sähköpörssien yhteinen ohjausryhmä on ilmoittanut, että sähkön vuorokausimarkkinoilla ei voida siirtyä 15 minuutin kaupankäyntijaksoon suunnitellusti kesäkuussa, koska kaikki osapuolet eivät ole valmiita omien tietojärjestelmien osalta. Uusi käyttöönottopäivämäärä on 30.9.2025.
Itämeren alueen kantaverkkoyhtiöt julkaisevat tiekartan, joka yhdistäisi maat tehokkaalla ja kestävällä meriverkolla13.5.2025 15:31:44 EEST | Tiedote
Itämeren alueen EU-maiden kantaverkkoyhtiöt ovat kehittämässä yhteistä tiekarttaa, jossa maat yhdistettäisiin tehokkaalla ja kestävällä meriverkolla. Itämerellä arvioidaan olevan potentiaalia jopa 93 gigawatille merituulivoimaa. Turvallisuus ja suojaus ovat keskeisessä asemassa meri-infrastruktuuria suunnitellessa.
Olkiluoto 3:n järjestelmäsuojan kohteet valittu kaudelle 7/2025 – 202613.5.2025 13:03:14 EEST | Tiedote
Energiaviraston päätöksen mukaan Olkiluoto 3 -ydinvoimalaitoksen (OL3) järjestelmäsuojaan osallistuvien kohteiden hankinta on Fingridin tehtävä. Nykyinen OL3:n järjestelmäsuojajärjestely päättyy kesäkuun 2025 lopussa. Fingrid on kevään kuluessa järjestänyt tarjouskyselyn 1.7.2025 alkaen OL3-järjestelmäsuojaan osallistuvista kohteista. Ylläpitoon heinäkuun alusta vuoden 2026 loppuun on valittu seuraavat osapuolet: Kemira Chemicals Oy Metsä Board Oyj Neoen Storage Finland 1 Oy Sappi Finland Operations Oy Stora Enso Oyj Teollisuuden Voima Oyj UPM Communication Papers Oy Lisäksi uusia kohteita on suunniteltu liittyvän OL3:n järjestelmäsuojaan syksyn 2025 aikana, mikäli tarvittavien tiedonsiirtoyhteyksien toteutus osoittautuu mahdolliseksi. OL3:n järjestelmäsuojaan kytkettävä kokonaismäärä kasvaa 530 megawattiin (aiemmin 475 megawattia). Kohteiden päivittäinen käyttötilanne vaikuttaa siihen, millä teholla ne pystyvät kulloinkin osallistumaan ylläpitoon. Ylläpitoon valitaan kullekin vuorokau
Uusi pääsiirtolinja vahvistaa länsirannikon siirtokapasiteettia13.5.2025 11:00:05 EEST | Tiedote
Fingrid rakentaa Kristiinankaupungista Nokialle uuden 400 kilovoltin kantaverkon pääsiirtolinjan, joka edistää länsirannikolle voimakkaasti keskittyneen tuulivoimatuotannon sähkön siirtämistä eteläiseen Suomeen. Vuonna 2029 valmistuva Åback - Nokia -siirtoyhteys mahdollistaa uusia asiakasliityntöjä kantaverkkoon, parantaa koko sähköjärjestelmän käyttövarmuutta ja helpottaa siirtokeskeytyksiä.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom