Fingrid Oyj

Maintenance and construction work will limit electricity transmission capacity between Sweden and Finland in the summer

28.5.2024 15:00:00 EEST | Fingrid Oyj | Press release

Share

The transmission capacity of the cross-border electricity transmission connection between Northern Finland and Sweden will be lower than usual in the summer due to maintenance and construction work on transmission lines. The modifications and measurements carried out during the outage ensure the operational reliability and safety of the cross-border transmission connection.

Kuvan lähteenä mainittava Fingrid Oyj.

Work to improve the reliability and operational safety of the cross-border transmission connection will be carried out on transmission lines in northern Sweden in early summer, which is why part of the cross-border electricity transmission connection between Finland and Sweden will be out of service. During the limitation period, the transmission capacity of the connection from Finland to Sweden will be 300 megawatts (usually 1100 megawatts) and the transmission capacity of the connection from Sweden to Finland will be 200 megawatts (usually 1200 megawatts). The estimated duration of the interruptions is just over three weeks.

A similar restriction will be repeated in July and August, when the construction work of the Aurora Line transmission line will continue with an interruption of approximately four weeks. The Aurora Line is a new cross-border transmission connection implemented jointly by Fingrid and Svenska kraftnät, which, when completed in 2025, will significantly increase transmission capacity between Finland and Sweden. The Aurora Line transmission line is 380 kilometres long and runs from the Pyhänselkä substation in Muhos all the way to Messaure in Sweden.

The construction of the first phase of the Aurora Line began in autumn 2022 in Finland. In addition to increasing transmission capacity, Aurora Line will improve the security of electricity supply and the resilience of the electricity system not only in Finland and Sweden, but also more widely in the entire Baltic Sea region.

Restrictions on cross-border transmission connections increase sensitivity to fluctuations in electricity prices

During border capacity limitations, sensitivity to fluctuations in electricity prices increases. In particular, price fluctuations may be greater than usual in situations where there are simultaneously several influencing factors, such as low or high wind power production, disturbances in power plants or disturbances in other transmission connections.

In addition, there will be several outages in Ostrobothnia during the summer because of construction work strengthening the main grid , during which the maximum production of wind power will have to be limited regionally by a maximum of 2,000 megawatts due to system security.

"Cross-border transmission connections to Sweden and Estonia are very important for the functioning of the electricity market and the system security of the Finnish electricity system. At the moment, the main grid is being built at a rapid pace in Finland and Sweden, which also causes restrictions and interruptions in electricity transmission. Fingrid and Svenska kraftnät work closely together on both sides of the border to ensure that necessary outages cause as little inconvenience as possible," says Tuomas Rauhala, Director of Power System Operations at Fingrid.

Additional information:

Senior Advisor Timo Kaukonen, phone +358 40 545 2124

Unit Manager Mikko Piironen, phone +358 50 599 0141

Email addresses are in the format etunimi.sukunimi@fingrid.fi

Keywords

About Fingrid Oyj

Fingrid is Finland’s transmission system operator. We secure reliable electricity for our customers and society, and we shape the clean and market-oriented electricity system of the future.

Fingrid delivers. Responsibly.
www.fingrid.fi

Alternative languages

Subscribe to releases from Fingrid Oyj

Subscribe to all the latest releases from Fingrid Oyj by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from Fingrid Oyj

Sähkön tuotannon ja kulutuksen kehitysnäkymät päivitetty – sähkönkulutuksen kasvu konkretisoituu30.9.2026 14:05:20 EEST | Tiedote

Suomen sähkönkulutuksen kasvu on voimistumassa, Fingrid arvioi uudessa ennusteraportissaan. Fingridin näkemys sähkönkulutuksen pitkän aikavälin kasvun suuruudesta on säilynyt pääosin ennallaan, mutta erityisesti datakeskushankkeiden eteneminen on vahvistanut näkymää kasvun toteutumisesta. Sähkönkulutuksen kasvu korostaa tarvetta kotimaisen sähköntuotannon sekä säästä riippumattoman säätövoiman kasvulle.

Metsälinja 2 -voimajohtoyhteys vastaa sähköistyvän Suomen tarpeisiin29.9.2026 10:52:00 EEST | Tiedote

Fingrid on tehnyt investointipäätöksen 400 kilovoltin Metsälinja 2 -voimajohtoyhteydestä Vaalasta Jämsään. Noin 350 kilometrin mittainen yhteys vahvistaa sähkönsiirtoa Pohjois- ja Etelä-Suomen välillä, mahdollistaa uuden sähköntuotannon ja kasvavan kulutuksen liittämisen kantaverkkoon sekä parantaa sähköjärjestelmän käyttövarmuutta. Yhteys on tarkoitus ottaa käyttöön vuonna 2030.

Utökningen av elsystemet ökar kostnaderna – stamnätsavgifterna höjs i början av nästa år med 4 procent28.9.2026 11:41:47 EEST | Pressmeddelande

Stamnätsbolaget Fingrid kommer att höja avgifterna för stamnätstjänster med 4 procent i början av 2027. Orsaken till höjningen är ett omfattande proaktivt investeringsprogram för framtida kundbehov samt ökade kostnader i det växande elsystemet. En förstärkning av stamnätet öppnar för industriella investeringar i Finland, vilket stöder den ekonomiska tillväxten.

Growth in the power system increases costs – main grid service fees will rise by 4 per cent at the beginning of the year28.9.2026 11:41:47 EEST | Press release

Transmission system operator Fingrid will raise main grid service fees by 4 per cent as of the beginning of 2027. The increase is driven by a substantial investment programme anticipating future customer needs and the rising costs of the expanding power system. Strengthening the transmission grid supports economic growth by enabling industrial investments in Finland.

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye