The planning of Mariantunneli tunnel connecting bicycle traffic routes is progressing
The planning the old Maria Hospital area and Mariantunneli tunnel passing under Mechelininkatu has reached the general planning phase. The tunnel is a significant part of the Baana network. It will connect Länsibaana, which has been planned to extend to Kivenlahti in Espoo, to the Baana network of South Helsinki. The plan will proceed to political decision-making in January and will be open for comments until 25 November.

A key part of a continous Baana network
Mariantunneli is a significant part of the Baana network consisting of the main bicycle traffic connections. It will connect the original Baana, which was built in a railway shaft, to the planned Länsibaana running towards Lauttasaari and Espoo. The tunnel will provide clear, safe and continuous routes for east-west bicycle traffic and improve connections to other Baana routes in South Helsinki.
The tunnel, which is about 200 metres long, is also intended for pedestrians. Passage from the Lapinlahti area will become smoother, as cyclists and pedestrians can avoid crossing the busy Mechelininkatu street and waiting at traffic lights. On average, about 36,000 vehicles pass through Mechelininkatu at Lapinlahdenkatu on an autumn weekday. Ambulances have also been taken into account in the planning so they can drive into the tunnel, if necessary.
In addition to ceiling lights, the tunnel has been designed with booster lighting, the purpose of which is to increase the sense of safety. The colour of the wall-mounted lighting can be changed remotely according to the seasons or holidays, for example. The visual look will be refined in further planning.
The implementation of the traffic arrangements in accordance with the general plan will cost a total of approximately EUR 19 million.
Bicycle street proposed for Lapinlahdentie
The tunnel starts from the original Baana between Kamppi and Ruoholahti at Lapinlahdentie. It rises to the ground on Lapinlahdentie at the southern edge of the street.
In the plan, a bicycle street is proposed for Lapinlahdentie, where the driving speed must be adapted to the pace of bicycle traffic. Lapinlahdentie will have 24 parking spaces and four parking spaces for pick-up and drop-off traffic. In the current state, there is parking space for about 40 cars at the northern edge of the street and about 30 cars on the southern edge.
The culturally and historically valuable environment has been taken into account in the planning. The stone wall of the Orthodox cemetery built in the 19th century must be demolished for the duration of the construction work, but it will be documented and restored after the construction of the tunnel.
Traffic plan to be discussed by the Urban Environment Committee in January
A change in the local detailed plan for the former Maria Hospital area became valid in January 2023. In the change, a preliminary survey was carried out of the tunnel, and its indicative location was presented. At that time, the Urban Environment Committee decided that the implementation of the tunnel will be prepared for in the city’s 10-year investment programme at the end of the 2020s.
The tunnel’s traffic plan will be discussed by the Urban Environment Committee in January 2025. The general plan will be decided by the City Council. More detailed street and construction planning will begin once the City Council has approved the general plan.
Keywords
Contacts
Teppo Pasanen
Traffic engineer
City of Helsinki
09 310 37123
teppo.pasanen@hel.fi
Technical planning:
Raila Hoivanen
Project Manager
City of Helsinki
09 310 37482
raila.hoivanen@hel.fi
Links
Alternative languages
Subscribe to releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Subscribe to all the latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Helsingin kaupunki, kaupunkiympäristön toimiala
Kulosaaren ja Herttoniemen välinen pätkä Itäbaanaa valmistui etuajassa18.6.2025 10:35:09 EEST | Tiedote
Kilometrin verran uutta kaupungin laadukkainta baanaa on nyt valmiina Tupasaarentien ja Hiihtäjäntien välillä. Urakka valmistui kuukauden etuajassa.
Kaupunkiympäristölautakunnan päätöstiedote 17.6.202517.6.2025 18:59:43 EEST | Tiedote
Helsingin kaupunkiympäristölautakunta kokoontui tiistaina 17.6.2025 kautensa ensimmäiseen kokoukseen. Kokouksen päätöstiedote (yhteenveto tehdyistä päätöksistä) on julkaistu kaupungin verkkosivuilla: Päätöstiedote » Päätöstiedote näkyy verkkosivuilla siihen asti kun kokouksen pöytäkirja julkaistaan. Pöytäkirja korvaa valmistuttuaan päätöstiedotteen.
Esplanadilta joudutaan poistamaan vaarallinen puu16.6.2025 11:29:48 EEST | Tiedote
Puu on kaatumisvaarassa huonon kuntonsa vuoksi. Puu poistetaan juhannusviikon aikana.
Föregångare inom byggande – Blåbärslandet får Finlands första service- och lagerbyggnad tillverkad av återvunnet material13.6.2025 14:48:56 EEST | Pressmeddelande
I Blåbärslandet i Helsingfors färdigställs i slutet av juni en byggnad som till största delen är tillverkad av återanvända byggnadsdelar. Det är fråga om Helsingfors stads pilotprojekt vars lärdomar kommer att utnyttjas även i andra byggprojekt i framtiden.
Rakentamisen edelläkävijä – Suomen ensimmäinen uudelleenkäytetyistä materiaaleista rakennettu huolto- ja varastorakennus valmistuu Mustikkamaalle13.6.2025 14:48:56 EEST | Tiedote
Helsingin Mustikkamaalle valmistuu kesäkuun lopussa rakennus, joka on suurimmaksi osaksi valmistettu uudelleenkäytetyistä rakennusosista. Kyseessä on Helsingin kaupungin pilottiprojekti, jonka oppeja hyödynnetään tulevaisuudessa myös muissa rakennushankkeissa.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom